Barcelona Power Maintenance and Network Upgrade, scheduled 1 week ago

Our Datacenter has announced a power maintenance in Barcelona, bitNAP.

Further, we will in the same window conduct a network upgrade to increase capacity and add redundancy to our network.

Description:

As part of the final phase of the data center upgrade and expansion, on July 31st, work will

be carried out to expand the UPS system which protect Branch B.

Network uplinks may be impaired during this time and services unreachable.

Start Time Window: Friday, 31.07.2026 - 06:00

End Time Window: Friday, 31.07.2026 - 10:00

Duration: up to 2h.

Location: bitNAP Barcelona.

Update:

The Upgrade was completed.